Fairfield Rd Resurfacing

Limits: From Nippersink Rd to IL132 in Round Lake, Round Lake Beach, Round Lake Heights, and Lake Villa.

Description: Asphalt resurfacing and installation of bike friendly shoulders

Construction

Current Information



The Fairfield Rd Resurfacing Project has started. The work will include storm sewer (No Road Crossings) and driveway culvert pipe replacement. Work will also include Curb & Gutter replacement. Both sections of roadway will be affected by this work. This work will likely last a few weeks.


-Fairfield Rd (Nippersink Rd to IL RTE 134) – Backfilling of newly poured curb.

-Fairfield Rd (Monaville Rd to IL RTE 132) – Curb inlet repair, pouring replacement curb, ditching work at driveway culverts that were replaced.



Project Images